We offer comprehensive services aiming to help you succeed
We give you 100 percent guarantee that if you fail the test unluckily, we will return full refund to you. But this kind of situations is rare, which reflect that our 1Z0-244 valid practice files are truly useful. The prices of the study material are inexpensive. We also give you some discounts with lower prices. That is a part of our services to build great relationships with customers. So they also give us feedbacks and helps also by introducing our 1Z0-244 : Oracle EBS R12: Advanced Supply Chain Planning updated study guide to their friends. We sincerely hope you can have a comfortable buying experience and be one of them.
Three versions of study material combine with the assistance of digital devices to fit your needs
Three versions of our Oracle Applications Oracle EBS R12: Advanced Supply Chain Planning updated study guide are PDF & Software & APP versions. Their features are obvious: convenient to read and practice, supportive to your printing requirements, and simulation test system made you practice the Oracle EBS R12: Advanced Supply Chain Planning study pdf material seriously. Besides, you can use the 1Z0-244 test study training on various digital devices at your free time and do test questions regularly 2 to 3 hours on average. In this way you can study at odd moments and make use of time more effective. We promise you here that as long as you pay more attention on points on the Oracle 1Z0-244 valid practice file, you can absolutely pass the test as easy as our other clients. After ordering your purchases, you can click add to cart and the website page will transfer to payment page, you can pay for it with credit card or other available ways, so the payment process is convenient. With the help of Oracle Applications Oracle EBS R12: Advanced Supply Chain Planning study pdf material and your hard work, hope you can pass the test once!
Instant Download: Our system will send you the 1Z0-244 braindumps file you purchase in mailbox in a minute after payment. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Be your honest and reliable friends and keep you privacy against any danger
If you input your mailbox address, we will send you a message including discount code, which can lower your price, and other updates of the Oracle EBS R12: Advanced Supply Chain Planning study pdf material will be send to you even you bought Oracle EBS R12: Advanced Supply Chain Planning updated practice files already. We also welcome your second purchase if you have other needs. You can still have other desired study material with bountiful benefits. Any information you inputted on our website will be our top secrets, and we won't reveal them in any case. All secure protections are offered to protect your privacy against any kinds of threats.
There is an old saying goes that one is never too old to learn, so in this lifetime learning period, getting a meaningful certificate is a chance to help you get promotion or other benefits. Passing the Oracle EBS R12: Advanced Supply Chain Planning certification is absolutely an indispensable part to realize your dreams in IT area. There are so many IT material already now, so it is necessary for you to choose the best and most effective one. The 1Z0-244 : Oracle EBS R12: Advanced Supply Chain Planning latest pdf material of us are undoubtedly of great effect to help you pass the test smoothly.
Oracle 1Z0-244 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Optimization & Advanced Features | 15% | - Alternate Resources, BOMs, and Substitutions - Cost-Based Optimized Plans - Penalty Factors and Optimization Parameters |
| Topic 2: Modeling the Supply Chain | 20% | - Organizations, Items, and Calendars - Bills of Material and Routings - Resources, Sourcing Rules, and Assignment Sets - Lead Times and Supply Chain Structure |
| Topic 3: Planning Fundamentals & Architecture | 15% | - ASCP Architecture & Planning Methods - Planning Data Collection & Setup - ASCP Overview & Key Capabilities |
| Topic 4: Unconstrained Planning | 15% | - Exceptions and Recommendations - Planner Workbench Navigation - Creating and Running Unconstrained Plans |
| Topic 5: Plan Analysis, ATP & Execution | 15% | - Pegging, Supply/Demand Review - Releasing Planned Orders - Key Performance Indicators & Metrics - Available-to-Promise (ATP) Functionality |
| Topic 6: Constrained Planning | 20% | - Decision Rules and Constraints Configuration - Analyzing Late Demand and Supply Issues - Enforcing Capacity and Material Constraints |
Oracle EBS R12: Advanced Supply Chain Planning Sample Questions:
1. A constrained plan with the Enforce Capacity Constraints option is run and you are asked to analyze Late Demands in the plan.
Which two exception messages are critical In the above case?
A) Late Replenishment for Sales Order
B) Sourcing Split Percentage violated
C) Late Replenishment for Forecast
D) Demand quantity not satisfied
E) Order is firmed late
2. Your client has a demand to be satisfied in the future. The plan is a constrained plan, and the Enforce Demand Due Dates check box Is enabled. The plan Issued a supply order to satisfy the above demand with the insufficient lead time exception message. The planning engine compressed the lead times for two of the machine resources to meet the demand due date. There are no other supply orders that have the same exception message.
Your client has the following requirements:
1) The processing times of any operation cannot be compressed.
2) There are no additional machine resources to use.
3) The customer for the above order is willing to receive the order within the minimal possible late days.
Identify the best option in the above scenario.
A) Firm the work order.
B) Run a constrained plan with the capacity constrained option enabled.
C) Buy new additional resources.
D) Run the same plan and change the default value of the MSO: Lead Time Control profile option.
E) Run an unconstrained plan.
3. Identify two correct product aggregation levels available In ASCP.
A) Organization
B) Product Family
C) Departments
D) Sales Orders
E) Item
F) Category
G) Forecast
4. Identify four costs from the source system that are considered by an ASCP Optimized Plan.
A) Item Cost
B) Resource Cost
C) Transportation Cost
D) Warranty Replacement Cost
E) Inventory Carrying Cost
F) Ordering Cost
5. During the data migration phase, there are items having routing with up to 10,000 sequence numbers. These need to be migrated to Oracle.
What specific action needs to be performed (If any) to migrate this data Into Oracle?
A) Set two routings: one primary (1-5000 steps) and the remaining steps with an alternate label.
B) You must Import the routing in two stages with 1-5000 and 5001-10000.
C) The highest allowed sequence number is 9999, therefore this limitation needs to be conveyed to the client before migration.
D) No specific action needs to be taken for importing data with 10,000 sequence numbers.
E) Set the BOM parameter "Numbering Method" with the required value.
Solutions:
| Question # 1 Answer: A,D | Question # 2 Answer: D | Question # 3 Answer: C,G | Question # 4 Answer: A,B,C,F | Question # 5 Answer: A |